Bewley Infant & Junior School

Bewley Infant and Bewley Juniors were Stockton-on-Tees Council’s last separate infant and junior schools. The project was to amalgamate these schools into one.

The works comprise of the construction of a single storey extension to the infant block to provide additional learning space, refurbishment and alterations to the infant school, car park extension, new playground and the demolition of the existing junior school building.

The contract was undertaken in 3 key phases to minimise disruption to the occupied school:-

  1. Nursery extension
  2. Infill extension to Courtyard 1, extension works adjacent Main Hall and completion of link corridors and internal alterations and refurbishment works to the existing Infants School
  3. Asbestos removals, services isolations and strip outs, soft strip outs and demolition of the existing Junior School block.

Liaison was maintained throughout the construction stage with the designated Contract Administrator, Clients representative and building users. Regular consultation about the progress of work was also provided with particular regard to the timings of when disruptive work may take place.

Client: Stockton-on-Tees Council

Value: £2.9 million

“I wish you could have seen the children’s faces when they saw inside the school, they love their classrooms and playground.”